Below is a project WBS with cost apportioned by percents.
3. Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be 5600,000. What are the estimated costs for the following deliverables?
a. Design?
b. Programming?
c. In-house testing?
What weaknesses arc inherent in this estimating approach?